P6还是MS Project - 来自国外工程咨询公司的观点0
本帖最后由 fanzhenyu 于 2012-1-6 16:16 编辑在别的论坛里看到的资料,觉得不错,分享给大家:
关于计划软件的比较和选择,某国外工程咨询公司提出了以下指南(详见附件 Construction_Scheduling-Primavera_vs_MSProject.pdf)
• Projects with over 500 activities → Primavera™ (P6). uyd y[n\
• Program-level analysis or simultaneous multiple project analysis → Primavera™ (P6).
• Multiple user interface (more than one person updating the schedule) → Primavera™ (P6).
• Projects with over $10 million worth of scope → Primavera™ (P6).
• Construction schedule oversight and detailed analysis → Primavera™ (P6).
• Non-construction projects or process-oriented schedules → MS Project™. (WW*yv.J
• Basic bar charts or timelines for display in MS PowerPoint™ presentation → MS Project™.